Total Contracts

8

All time

Active

3

Currently running

Pending

1

Awaiting start

Completed

2

Successfully closed

Total Value

$7.74M

USD equivalent

Sort:

Showing 8 of 8 contracts

CTR-2024-004Pending

Last-Mile Connections – Dakar Peri-Urban

SénéElec Contractors
Dakar Region
USD 670,000
Overdue
Progress0%
CTR-2024-005Draft

Grid Extension – Bamako Outskirts

Mali Énergie Contractors
Bamako District
USD 880,000
Overdue
CTR-2024-002Active

Streetlight Rehabilitation – Accra Metro

BrightPath Engineering
Greater Accra
USD 480,000
Overdue
Progress82%
CTR-2024-003Active

Substation Upgrade – Abidjan South

Électricité Côte d'Ivoire SARL
Abidjan District
USD 2,100,000
Overdue
Progress45%
CTR-2024-001Active

Rural Electrification – Northern Corridor

Volta Power Solutions Ltd
Northern Region
USD 1,250,000
Overdue
Progress68%
CTR-2023-021Completed

Metering Infrastructure – Lomé Central

TogoTech Solutions
Maritime Region
USD 215,000
Completed
Progress100%
CTR-2023-018Completed

Transformer Supply & Installation – Kumasi

PowerGrid West Africa
Ashanti Region
USD 390,000
Completed
Progress100%
CTR-2023-015Terminated

Solar Hybrid Mini-Grid – Tamale

SunPower Africa Ltd
Northern Region
USD 1,750,000
Terminated
Progress34%